Update – 14 February

The repair to the storm damage on Cell 5 is now complete and we are increasing the gas extraction to maximum. We have also completed the additional capping of the flank of the old Cell 4 and we are currently working to complete the capping of the top of this cell (see photo below). This work is over and above that requested by the EA.

This week we have also installed 10 additional pin wells into Cell 6 to increase gas capture from the new cell.