News

Update – 2 June 2025

The latest odour monitoring report for the week commencing 26 May 2025 has reaffirmed the ongoing minimal impact of odour from the Jameson Road landfill site on surrounding residential areas.

Update – 27 May 2025

The latest findings from weekly odour monitoring again confirm that the Jameson Road landfill site continues to play only a small role in the overall odour profile of the area.

Update – 21 May 2025

The latest findings from weekly odour monitoring again confirm that the Jameson Road landfill site continues to play only a small role in the overall odour profile of the area.

Update – 16 May 2025

The first set of results an the independent odour monitoring company have been published and show that odour levels are currently low, and appear to originate from a number of sources.

EA Releases Air Quality Monitoring Report

The biggest and longest study into air quality surrounding the Jameson Road land fill site has concluded that air quality is well within WHO safety standards - directly contradicting claims made by objectors that they are being poisoned.

Update – 2 May 2025

The new deep wells continue to work well and our gas contractors are fine tuning them on an ongoing basis to maximise performance. The independent odour monitoring is showing very little odour from our site over the last 10 days.

Update – 25 April 2025

Progressive restoration will start this spring/summer, with tree planting taking place in autumn/winter. The tree planting is a £411,000 programme which will involve the planting of 32,000 trees on the site.

Update – 17 April

The 11 new gas wells are continuing to perform well, but we are constantly fine tuning their settings to achieve maximum odour extraction.

Update – 11 April

Work is continuing in Cell 6. Our aim is to bring the cell up to approved contour levels as soon as possible so that we can get a permanent cap on it earlier, rather than wait for the completion of the site.

Update – 9 April

Last night the Environment Agency confirmed that the work to drill and install the 11 deep wells conformed with all conditions of the Suspension Notice and as such, a Withdrawal Notice was issued.

Update – 4 April

The 11 new deep gas wells in Cell 6 continue to work well and odour levels from the site are dropping. We anticipate that these will drop further as the wells are balanced.

Update – 1st April

All 11 wells are now connected up and functioning. There has already been a reduction in odour level - even though the wind has been blowing over Fleetwood today. The odour levels should drop further as the wells are balanced to maximise gas capture.

Update – 28 March

As promised, the drilling of 11 deep wells was completed today and these have now been connected to the gas capture infrastructure. These are now extracting gas and will be balanced to achieve maximum effectiveness.

Update – 26 March

For the last few days we have been preparing the site for the drilling of the 11 deep wells to rectify the odour problem from Cell 6. This work included infilling part of Cell 6 with soil to create a level platform to work from.

Update – 20 March

Over the last couple of days we have continued to prepare the site for the deep well drilling next week. This has mainly involved sealing the cell with clay.

Update – 14 March

Work on sealing Cell 6 with a thick layer of clay has progressed well with the good weather this week and it is now almost completed. We hope to have this finished early next week, ready for the deep gas extraction wells the week after.

Update – 11 March

As previously mentioned in our updates, we are planning to undertake work to further improve capping and to prepare the site for additional gas infrastructure.

Update – 7 March

Capping work on Cell 4 is well underway and, weather permitting, we hope to complete this by the end of next week.

Update – 21 February

Following a constructive meeting with Lorraine Beavers MP, we have taken on board her comments and have decided to withdraw our application for a permit variation.

Update – 14 February

The repair to the storm damage on Cell 5 is now complete and we are increasing the gas extraction to maximum. We have also completed the additional capping of the flank of the old Cell 4 and we are currently working to complete the capping of the top of this cell. This work is over and above that requested by the EA.